Projects delivered to specification, on schedule.
AL Furqan Corporation delivers engineering and construction projects for power utilities and public-sector organisations, from planning and mobilisation through execution, quality assurance and handover. Each completed project is supported by a certificate of completion issued by the client.
Completed projects
| Client | Project | Executed by | Contract value | Awarded | Status |
|---|---|---|---|---|---|
| National transmission utility | Foundations for new 500 kV circuit breakers and current transformers, 500 kV Grid Station Guddu | AL Furqan Corporation | Up to Rs 5 million | May 2026 | Completed |
| Power distribution utility | Sub-soil investigation for four 132 kV transmission line routes | Joint venture with MRCC | Rs 5 to 25 million | Jul 2025 | Completed |
| Power distribution utility | Re-routing of the 132 kV Shikarpur–Arain Road transmission line, Sukkur: pole construction, erection and stringing | Joint venture with MRCC | Rs 5 to 25 million | Jun 2025 | Completed |
| Power distribution utility | Emergency restoration of the 132 kV New Rohri–Old Rohri transmission line | AL Furqan Corporation | Up to Rs 5 million | Apr 2025 | Completed |
| Power distribution utility | Field survey for the re-routing of three 132 kV transmission lines | AL Furqan Corporation | Up to Rs 5 million | Apr 2025 | Completed |
| Power distribution utility | Emergency restoration of the 132 kV New Rohri–Nara-I and New Rohri–Solar Power Plant transmission lines | AL Furqan Corporation | Up to Rs 5 million | Apr 2025 | Completed |
| Power distribution utility | Tower foundations, erection and stringing, 132 kV double-circuit TPS Guddu–Daharki transmission line (2.2 km) | AL Furqan Corporation | Rs 5 to 25 million | Jan 2025 | Completed |
| National transmission utility | Reconstruction of the sewerage system, 500 kV Grid Station Jamshoro | AL Furqan Corporation | Rs 5 to 25 million | May 2024 | Completed |
| Power distribution utility | Rehabilitation of two collapsed towers, 132 kV Ratodero–Naudero transmission line | AL Furqan Corporation | Up to Rs 5 million | Nov 2023 | Completed |
| National transmission utility | Interior refurbishment of engineering offices, Hyderabad | AL Furqan Corporation | Up to Rs 5 million | Nov 2023 | Completed |
| Power distribution utility | Tower reconstruction and restringing, 132 kV Lodra–Madeji–Larkana transmission line | AL Furqan Corporation | Up to Rs 5 million | Jul 2023 | Completed on schedule · performance certificate |
| Power distribution utility | Tower reconstruction and restringing, 132 kV Lodra–Garhi Yaseen transmission line | AL Furqan Corporation | Up to Rs 5 million | Jul 2023 | Completed on schedule · performance certificate |
| Power distribution utility | Rehabilitation of towers on the 132 kV Mirpur Mathelo, 132 kV Guddu Left–Daharki and 66 kV Rohri–Nara-I transmission lines | AL Furqan Corporation | Rs 25 to 50 million | May 2023 | Completed on schedule · performance certificate |
| Power distribution utility | 11 kV switch room, 132 kV Grid Station Sukkur City | Joint venture with MRCC | Rs 5 to 25 million | Nov 2022 | Completed |
| Power distribution utility | Equipment foundations and switchyard trenches for a 132 kV line bay, 132 kV Grid Station Nara-I | Joint venture with MRCC | Up to Rs 5 million | Nov 2022 | Completed |
| Power distribution utility | Tower foundations, erection and stringing, 132 kV Lodra–Madeji transmission line (four locations) | AL Furqan Corporation | Up to Rs 5 million | Jun 2022 | Completed on schedule · performance certificate |
Contract values are shown in bands. Projects executed in joint venture with M.R Construction Company (MRCC), our parent company, are indicated as such.
Projects in progress
| Client | Project | Executed by | Contract value | Awarded | Status |
|---|---|---|---|---|---|
| Power distribution utility | Tower foundations, RCC pile foundations, erection, stringing, testing and commissioning, 132 kV Shahdad Kot–Garhi Khero transmission line (Lot V) | Joint venture with MRCC | Above Rs 100 million | Oct 2025 | Under execution |
Registrations and licences
Copies of registration documents are available on request.
Pakistan Engineering Council
Licensed constructor, Category C-4, Licence No. 18643, valid to 30 June 2028. Twenty-seven specialisations across civil, building, electrical and solar works.
FBR and SRB
Active taxpayer with the Federal Board of Revenue, and registered with the Sindh Revenue Board for sales tax on services since 2022.
Joint venture with MRCC
A registered joint venture with M.R Construction Company (MRCC), the parent company, for larger and multi-discipline projects.
Project delivery approach
Projects are executed with the shared plant, machinery and engineering team of the MRCC group, under one management and one quality standard.
Planning and mobilisation
Site survey, work programme, resource allocation and timely mobilisation of men and equipment.
Execution and supervision
Works carried out under qualified engineers, with daily supervision and progress reporting to the client.
Quality, health and safety
Work executed to approved specifications and drawings, with safe working practices on every site.
Testing and handover
Inspection, testing and complete documentation, closing with the client's certificate of completion.
Certificates and testimonials
Clients have issued performance certificates for our completed transmission line works, each confirming completion to approved drawings and specifications, within the original completion date, with no delay and no liquidated damages. Copies are available on request.
Management
Nasir Ahmed Panhwar
Founder and Chairman of M.R Construction Company (MRCC), the parent company.
Muhammad Furqan Nasir
Chief Executive Officer, AL Furqan Corporation.